1061. Each work should be planned with respect to :
A. Manner of execution of the work
B. Urgency of the work
C. Availability of resources
D. All of the above *
1062. Technical planning is carried out for the :
A. Preparation of detailed drawings
B. Preparation of detailed estimate
C. Planning resource and initiating procurement action
D. All of the above *
E. None of the above
1063. Planning of resources belongs to the _________ planning :
A. Pre-tender *
B. Post-tender
1064. Pre-tender planning is undertaken by the contractor after receipt of tender and before submitting a bid:
A. Yes *
B. No
1065. The terms “time and progress chart” and “:
A. Bar chart
B. Gantt chart
C. Critical path method chart
D. Modified milestone chart
E. All of the above *
1067. The process of calculating the resource requirement of a project is known as :
A. Scheduling
B. Co-ordinating
C. Resource aggregation *
D. All of the above
1068. Military type of organisation is known as :
A. Line organisation *
B. Functional organization
C. Line and staff organization
D. Line staff and functional organization
E. None of the above
1069. In a line organization :
A. Responsiblity of each individual is fixed
B. Discipline is strong *
C. Quick decision are taken
D. All of the above
E. None of the above
1070. F.W taylor introduced a systerm of organisation known as :
A. Line organisation
B. Functional organisation *
C. Line and staff organisation
D. None of the above