491. Which of the following is not an adaptation criteria for software projects ?
A. Size of the project
B. Customers Complaints
C. Project staff
D. Mission criticality

Explanation: These can vary from client to client.

492. A technique for performing quantitative analysis of progress is known as______________________?
A. BCWS
B. EVA
C. BAC
D. CBSE

Explanation: The earned value system provides a common value scale for every task, regardless of the type of work being performed. The total hours to do the whole project are estimated, and every task is given an earned value based on its estimated percentage of the total.
advertisement

493. What is used to determine the recommended degree of rigor with which the software process should be applied on a project ?
A. Degree of Rigor
B. Adaptation criteria
C. Task Set
D. Both degree of Rigor and adaptation criteria

494. Which of the following is a project scheduling method that can be applied to software development ?
A. PERT
B. CPM
C. CMM
D. Both PERT and CPM

Explanation: Program evaluation and review technique (PERT) and critical path method (CPM) are two project scheduling methods that can be applied to software development.

495. What evaluates the risk associated with the technology to be implemented as part of project scope ?
A. Concept scoping
B. Preliminary concept planning
C. Technology risk assessment
D. Customer reaction to the concept

496. Ensuring that no more than the allocated number of people are allocated at any given time in Software Scheduling is known as ________________?
A. Time Allocation
B. Effort Validation
C. Defined Milestone
D. Effort Distribution

497. Every task that is scheduled should be assigned to a specific team member is termed as_________________?
A. Compartmentalization
B. Defined milestones
C. Defined responsibilities
D. Defined outcomes

Explanation: These responsibilities are domain specific.

498. What is a collection of software engineering work tasks, milestones, and deliverables that must be accomplished to complete a particular project ?
A. Task set
B. Degree of milestone
C. Adaptation criteria
D. All of the mentioned

499. A project usually has a timeline chart which was developed by_________________?
A. Henry Gantt
B. Barry Boehm
C. Ivar Jacabson
D. None of the mentioned

Explanation: Timeline chart, also called a Gantt chart was invented by Henry Gantt, an industrial engineer in 1917 .

500. _________________ view shows the system hardware and how software components are distributed across the processors in the system ?
A. physical
B. logical
C. process
D. all of the mentioned

Explanation: A physical view is implemented by system engineers implementing the system hardware.