371. Which of the following is not a part of process change ?
A. Introducing new practices, methods or processes
B. Introducing new team members to existing project
C. Introducing or removing deliverable
D. Introducing new roles or responsibilities

Explanation:
Adding more developers aid to process completion rather than changing it.

372. It is always best to start process analysis with a new test model ?
A. True
B. False

Explanation:
It is always best to start process analysis with an existing model. People then may extend and change this.

373. The CMMI assessment is based on a x-point scale. What is the value of x ?
A. 0
B. 2
C. 4
D. 6

Explanation:
Not performed, performed, managed, defined, quantitatively managed, and optimizing are the six points.

374. Which of the following is not a SQA plan for a project ?
A. evaluations to be performed
B. amount of technical work
C. audits and reviews to be performed
D. documents to be produced by the SQA group

Explanation:
All other options support a SQA plan

375. ____________ states that, where appropriate, adequate statistical techniques are identified and used to verify the acceptability of process capability and product characteristics?
A. ISO 9001
B. ISO 9000-4
C. CMM
D. All of the mentioned

Explanation:
ISO 9001 states that, where, appropriate adequate statistical techniques are identified and used to verify the acceptability of process capability and product characteristics.

376. Which of the following requires design control measures, such as holding and recording design reviews and qualification tests ?
A. CMM
B. ISO 9001
C. ISO 9000-3
D. None of the mentioned

Explanation:
ISO 9000-3 states that the supplier should carry out reviews to ensure the requirements are met and design methods are correctly carried out.

377. Which of the following is not a maturity level in CMM ?
A. Design
B. Repeatable
C. Managed
D. Optimizing

Explanation:
The CMM is organized into five maturity levels as namely: Initial, Repeatable, Defined, Managed and Optimizing.

378. CO policy in CMM means___________________?
A. The leadership practices in Commitment to Perform
B. The organizational structure (groups) practices in Ability to Perform
C. The policy practices in Commitment to Perform
D. The planning practices in Commitment to Perform

379. The ISO 9000 series of standards is a program that can be used for external quality assurance purposes ?
A. True
B. False

Explanation:
The ISO 9000 series of standards is a set of documents

380. What is not included in prevention costs ?
A. quality planning
B. formal technical reviews
C. test equipment
D. equipment calibration and maintenance

Explanation:
The cost of quality includes all costs incurred in the pursuit of quality or in performing quality-related activities.

NOTE
IF YOU THINK ANY OF THE MCQ ABOVE IS WRONG.
PLEASE COMMENT WITH CORRECT ANSWER AND ITS DETAIL EXPLANATION IN COMMENT BOX.
THANK YOU